Engineering
Services Division - City of Concord,
NH
|
|

|
CIP35 – US
Route 3 Corridor North Project – Phase II Update:
July 09, 2010 Update:
The Phase
II section of the US Route 3 corridor has reached substantial
completion. The contractor will be removing equipment and construction signs from
the site. The Phase III section of North
State Street; from Lake Street to Palm Street is currently out to the
bidding process. The City will open bids on Friday, July 23rd and award the
next Phase shortly thereafter. Thanks to all the residents, commuters, cyclists
and pedestrians for their patience during the Phase II construction.

July 01, 2010 Update:
Next week
on the U.S. Route 3 corridor reconstruction project, the contractor will
be observing the Independence Day holiday and as such, no work will be occuring on Monday, July 5th. The remainder of the week
will entail completion of the sidewalk paving and loam placement. We also
tentatively expect long line and crosswalk striping in the section base paved
this year, from Knight Street to Lake Street. One-lane traffic conditions
will persist throughout the week in the aforementioned section of North State Street,
delays are to be expected.

June 25, 2010 Update:
Work
on the Phase II section of the Route 3 corridor continues to progress, with
next week scheduled for paving of sidewalks and construction of concrete ADA tipdown
ramps. We also expect to begin loam placement, with hydro seeding soon to
follow, and general site cleanup. As with past weeks, this work will require
one lane traffic conditions to persist on North State Street; from Knight Street to Lake Street.
National
Grid and R. H. White Construction will begin work on Lake Street to upgrade their main and services
to high pressure. This work will require one-lane traffic on Lake St. with minor
delays to motorists to be expected.

June 18, 2010 Update:
Next
week on the Route 3 reconstruction project; the contractor will be continuing
efforts to reconstruct and repave driveway aprons. Sidewalks have been
excavated to subgrade and we anticipate crushed
gravel placement and grading as well during the upcoming week. Catch basin
grates have been raised to base pavement grade in the past week, with manhole
frames and water valve boxes soon to follow. This work will be taking place on North State Street;
between Knight Street
and Lake Street.
One-lane traffic conditions will continue throughout the week, with minor
traffic delays to be expected. We thank you for your patience during traffic
delays due to the reconstruction project.

June 11, 2010 Update:
With
the completion of the binder course pavement and installation of vertical
granite street curbing completed, the contractor will now focus efforts on
constructing sidewalks and driveway aprons. This work will be occuring on North
State Street; from Knight Street to Lake Street. One-lane traffic conditions
will persist throughout this construction and delays are to be anticipated in
this area. With the road now paved, we would ask that the motoring public
respect everyone's safety and please slow down as you commute through
the work zone.

June 4, 2010 Update:
With
the section of North State Street
and Knight Street
newly base paved, the contractor will now focus efforts on reseting vertical granite street curbing, addressing
driveways and building sidewalks. These efforts will still require one
lane traffic conditions, and delays are to be expected. Your
patience is greatly appreciated as we continue to construct these much
needed improvements to the North
State Street corridor.
National
Grid and R. H. White Construction will be wrapping up the construction on K Street and Hillcrest Avenue
shortly and final restoration of disturbed areas should follow soon after.

May 28, 2010 Update:
Next
week the contractor will be fine grading and base paving the section of North State Street
recently box constructed; from Knight
Street to Lake Street and Knight Street itself. One lane
traffic conditions will persist in this area, with major delays anticipated
during hours of operation; typically 7 a.m. to 7 p.m. The public is advised to
seek alternate routes whenever possible.
National
Grid and R. H. White Construction continue gas service relays to customers on
Peabody, K and View Streets. Minor traffic delays are to be expected on the
affected streets.

May 21, 2010 Update:
Next week
the contractor will continue road box excavation on North State Street; between Lake Street and Knight Street. As with the past week,
traffic will be restricted to a single lane during hours of operation,
typically 7 AM to 7 PM. Major delays are to be anticipated and we recommend the
public seek alternate routes, whenever possible.
Work will
also begin on Knight Street
next week, with the removal of the south bound slip lane to North State Street, and box construction
extending three hundred feet west from North State Street. The remainder
of the pavement will be reclaimed to Hutchins Street. Please be advised that
their will be a granite curb "bumpout"
constructed in future weeks at Knight and Hutchins Streets in an effort to
"tee" the intersection and manage traffic speeds on Knight Street.
Temporary reflective orange pylons have been put in place representing the new
intersection alignment in an effort to prepare motorists for this future
improvement.
National
Grid and R. H. White Construction continue relaying gas services to
the new high pressure mains installed on the side streets of North State Street, in the upcoming Phase
3 section. Minimal traffic disruptions are to be expected in these areas.

May 7, 2010 Update:
With
the completion of drainage and sanitary sewer work, the contractor will begin
construction of the road box. This work will entail removal of the asphalt road
surface, underlying concrete slabs, excavation of the existing materials
beneath, and placement of new gravel base courses. This work will be taking
place on North State Street;
between Knight Street
and Lake Street.
The public is advised that travel will be restricted to one-lane at all hours
of operation and major delays are to be expected in the affected area. Please
seek an alternate route, if possible.
National
Grid and R. H. White Construction have completed gas main installations on the
side streets off of North State
Street, and will begin relaying individual gas
service lines to customers in these same neighborhoods. Minor traffic
disruptions are to be anticipated related to this work.
April 30, 2010 Update:
With
the completion of the new storm sewer trunk line, the contractor will continue
focus upon installation of new catch basins in the section of North State Street
between Knight Street
and Lake Street.
Also upcoming will be the replacement of deficient sanitary sewer services in
the same area noted above. As with past weeks, traffic flow will be restricted
to one-lane during hours of operation. The public is advised to expect delays
and seek alternate routes, whenever possible.
National
Grid and R. H. White will also continue work on new gas main and service
installations in and on the side streets off North State Street. This current
work will allow National Grid to retire the old cast iron gas main in the third
phase of the Route 3 reconstruction project, thereby reducing or eliminating
future conflicts with planned storm sewer infrastructure improvements.

April 23, 2010 Update:
Next week
the contractor will continue to install the new storm sewer trunk line and
drainage structures in North State
Street; from Knight Street to Lake Street. As with prior weeks, the
traffic flow will be restricted to one-lane, expect delays in this area.
National Grid and R. H. White Construction will continue with gas main and
service relays in North State
Street and side roads as well.

April 16, 2010 Update:
Next
week work will continue on the installation of new storm sewer infrastructure
from Knight Street
to Lake Street.
One-lane traffic conditions will persist in this area throughout the week, delays
are to be expected in this area. The contractor has substantially completed the outstanding
issues remaining from last construction season; clean up efforts from Sewalls Falls Road
to Hutchins Street
should be completed by next week.
National
Grid and their contractor, R. H. White, has begun to
relay gas services in anticipation of the Phase III work to North State Street. They will be working
on North State Street, from Lake Street to McGuire Street on services and will
be laying new main and services on side streets including; Lake Street, Clarke
Street, Fisher Street, Edgemont Street, Engel Street, Peabody Street, View
Street, K Street, and Hillcrest Avenue. Traffic delays in these areas are
to be anticipated as well.

April 9, 2010 Update:
During
the next week of construction on North
State Street, the contractor will continue
installation of new storm sewer infrastructure from Knight Street to Lake Street. One lane traffic conditions
will persist throughout the week in this area. Delays are to be expected,
alternate routes should be sought, if possible.
Completion
of minor punchlist items outstanding from last
season’s portion of the work continue to be addressed from Sewalls Falls Road to Knight Street. Hydro seeding and driveway
adjustments are completed in the above area and we anticipate final cleanup
shortly.

April 2, 2010 Update:
Due
to the rainstorms early last week, the installation of the new storm sewer
infrastructure was postponed until midweek. Work is currently underway on North
State Street, from Lake St. to Knight St. with single lane closures occurring
in this area during the hours of operation, typically from 7 a.m. to 5 p.m. Be
advised that there will be traffic delays in the aforementioned area of North
State Street.

March 26, 2010 Update:
With
the onset of the warmer spring weather, Engineering Services is pleased to
announce the resumption of CIP 35 - Route 3 Reconstruction Project. The City's contractor,
Continental Paving Inc, has returned to complete the Phase 2 section of the
corridor; primarily North State Street. Minor cleanup
items have begun to be addressed, including site cleanup, punchlist
items, and loam placement in preparation of seeding activities.
Next week
the contractor will begin construction of new storm sewer infrastructure
between Lake Street
and Knight Street.
This work will require single lane closures throughout the upcoming weeks in this
area. As with all road work of this nature, traffic delays are to be
anticipated. Please seek an alternate route, if possible. As a
friendly springtime safety reminder, please use caution and slow down
through this and all work zones encountered in your travels.
March 19, 2010 Update:
Please be
advised that the City’s contractor, Continental Paving, Inc. will resume the North State Street
reconstruction project on Monday, March 22, 2010. This work will occur on North State Street between Knight Street
north to Sewalls
Falls Road and will be light in nature. Minor
delays are to be expected. Major construction efforts (drainage installation,
removal of street pavement and underlying concrete slab, etc.) will not begin
in earnest until the week of March 29, 2010. Major delays are to be
expected on North State Street
between Lake
Street north to Knight Street (including Knight Street).
March 12, 2010 Update:
The
Engineering Services Division of the Community Development Department will host
a public meeting for Phase III of CIP#35 - U.S. Route 3 Corridor Improvements
on Thursday, March 18, 2009 at 6pm in City Council Chambers. The construction
schedule for this upcoming construction season will be discussed. The area of
U.S. Route 3 that will be affected by this construction phase will be from Palm Street to Lake Street. All
residents, commuters, local officials, community leaders, and neighborhood
groups are invited to attend. Any questions regarding this meeting should be
directed to Engineering Services at (603) 225-8520.
December 18, 2009 Update:
The
Route 3 reconstruction project has been suspended for the winter
months. It is expected that the new traffic signals will be activated
over this time period. The City would
like to acknowledge all the residents, pedestrians, cyclists and commuters that
have been impacted by the construction.
Their input and patience have been greatly appreciated throughout the
duration of the project.
December 11, 2009 Update:
With the
street and regulatory sign installations completed and the onset of winter
snow, major construction operations have ceased on the corridor. The contractor has only a few punch list
items to complete next week. This work will take place on North State Street, between Sewalls Falls Road
and Hutchins Street,
as weather permits. In traffic signal
news, the contractor has informed the City that the new signal
installation should take place next week at both the Fisherville Road/Bog Road and North State
Street/Sewalls Falls Road intersections.
The public is advised to expect minor delays in these two areas during
this work. Please stay tuned to www.concordnh.gov and the on-site message
boards for up-to-date changes regarding the corridor.

December 4, 2009 Update:
Next week,
the contractor will continue clean-up efforts on North State Street, from Sewalls Falls Road
to Knight Street. One-lane traffic conditions will continue in
this area. The regulatory street signs
and the remainder of the pavement markings will be installed next week as
well. In traffic signal news, the
contractor has informed us that a delay with the supplier will cause the new
signal installations at the Fisherville
Road/Bog Road and North State Street/Sewalls Falls
Road intersections to be postponed until the week of December 14th. Updates will be posted on the City’s website
at www.concordnh.gov and on the on-site
message boards.

November 25, 2009 Update:
Next
week the contractor will continue to pave sidewalks on North State Street, place loam in grass
panels and perform site clean-up from Sewalls
Falls Road south to Knight Street. One-lane traffic conditions will persist in
this area. With the closure of the Sewalls
Falls bridge, we expect
increased delay times during hours of operation; typically 7:00 AM to 5:00
PM. We will do everything in our power
to mitigate major delays, but with the anticipated increase in traffic volume to
the Route 3 corridor, they may prove unavoidable.
Upon
completion of the sidewalk paving, the contractor will complete the fog line
striping and cross walk bars on North
State Street and finish the line work at the Sewalls Falls Road
intersection. Permanent street sign
installations should also begin around the same time.
In traffic
signal news, we expect the mast arms and related signal equipment to begin to
be installed at both the Fisherville
Road/Bog Road and North State Street/Sewalls Falls
Road intersections in the next couple of weeks. Stay tuned to the City’s website www.concordnh.gov and the on-site message
boards for pending details.

November 20, 2009 Update:
Along the North
State Street corridor, the contractor continues to
build new sidewalks in the area between Sewalls Falls Road and Knight Street. One-lane traffic conditions will continue in
this area during the hours of operation; typically 7:00 AM to 5:00 PM. Residential driveway aprons are being paved
as quickly as possible. Many thanks to the public for bearing with us
during the radial granite curb installations.
With the continued warmer than normal fall weather, we expect to continue
paving the remainder of the driveways and then begin paving sidewalks next
week.

November 13, 2009 Update:
With the
completion of the new granite curbing, the contractor will continue to focus on
construction of the sidewalks along both sides of the North State Street corridor. Paving of the sidewalks and driveway aprons
should occur over the next two weeks.
The masonry subcontractor is expected on-site at the end of next week to
begin raising the catch basins and manhole frames to base grade for the winter.
Delays can be expected due to one-lane traffic conditions on North State Street from Sewalls Falls Road
to Knight Street. As always, the public’s patience is
appreciated as we work to complete the remaining construction prior to the
onset of winter.

November 6, 2009 Update:
With
the placement of thermoplastic pavement markings on the Fisherville Road section of the Route 3
reconstruction project, the contractor need only address final sign and traffic
signal installations and minor punch list items remaining in this area. Many thanks to the residents, businesses, pedestrians,
cyclists and commuters of Fisherville Road for their patience during the
delays created by the major construction efforts of this past season.
The
contractor has placed the "winter base" pavement on the North State Street
section of the work. Installation of
granite curbing and reconstruction of sidewalks will continue on both sides of
the street from Sewalls Falls Road
to Knight Street. The public can expect one-lane traffic
conditions and delays to persist in this area until the completion of the
work. Drivers are urged to slow down in
the construction zone, for their own safety and the safety of the workers.

Fisherville Road Ravine fill opposite Hutchins Street
October 30, 2009 Update:
Placement of the winter binder coarse pavement on North State Street,
from Sewalls Falls Road south
to Knight Street, is
planned for
today. Once this is accomplished, the contractor will focus on the
installation of vertical granite curbing in the newly paved area. One-lane traffic conditions will continue in
the work area and delays are to be expected, except as noted below.
With City
elections occurring on Tuesday, and the proximity of the work zone to
the polling locations, the contractor will not be working in North State Street
on Election Day (11/3). Work will
continue on the backfill and slope construction in the ravine opposite Hutchins Street. This work will not impact parking and will
have very little impact to traffic flow during hours of construction
operations. We expect two-lane traffic
conditions at all times.
On Fisherville Road,
placement of thermoplastic pavement markings, including cross walks, symbols
and stop bars will be continuing early next week.
October 23, 2009 Update:
Construction
of new storm sewer infrastructure continues on North State Street, from Tenney Street
to Knight Street. One-lane traffic conditions will continue in
this area with delays to be expected. We
encourage all who can seek alternate routes to do so. The pipe and drainage structure installations
are complete. The contractor is planning
to begin base paving of the graveled section of Route 3, from just north of Sewalls Falls Road
to Knight Street, during
the latter part of next week. We will
have better detail of the scheduling of this effort soon. Please stay tuned to the on-site message
boards or www.onconcord.com.
The final
striping of Fisherville Road
has been delayed due to scheduling conflicts. We hope to have the problems resolved and
begin the lane striping and regulatory sign installation early next week.
October 16, 2009 Update:
Due
to scheduling and weather conflicts, the final striping and sign installation
on Fisherville Road
has been delayed until next week. Minimal traffic disruptions should be
expected on Fisherville Road,
from Manor Road
to Sewalls Falls Road.
The road
box excavation on North State
Street should be complete next week. New storm sewer infrastructure installation
will continue from Tenney Street to Knight Street. One-lane traffic conditions will continue
during hours of operation (7:00 AM – 7:00 PM) and major delays are to be
expected. We appreciate the public’s
patience during this extensive road rehabilitation effort.

October 2, 2009 Update:
With the final wear course pavement placed on Fisherville Road,
from just south of Manor Road
to just south of Sylvester Street,
the contractor will focus efforts next week on driveway tie-ins. Final road striping and crosswalk markings
are expected the week of October 12th.
We thank the residents of this neighborhood and the commuters for their
patience throughout the duration of the construction in this area.
Along the North
State Street corridor, the contractor will
continue new storm sewer infrastructure installation; from Tenney Street
to Knight Street. Construction of the road box will continue as
well, from Parmenter
Road to Tenney Street. One-lane traffic conditions will persist
during hours of operation, and major delays are to be expected on North State Street
from Knight Street
to Parmenter
Road.
Motorists are advised to seek alternate routes whenever possible.

September 25, 2009 Update:
The
road box construction has begun on North
State Street.
The contractor is currently working in the area of Sewalls Falls Road and will be proceeding
south. The installation of new storm sewer infrastructure will also
continue from Tenney
Street to Hutchins Street. As many of the
commuters and residents of the impacted neighborhoods have experienced,
traffic delays are upwards of twenty to thirty minutes in length during peak
hours. We encourage drivers to seek alternate
routes whenever possible, as the major construction operations will continue
for several weeks.
On
the Fisherville Road
section of the reconstruction work, we are pleased to announce that the final
wear course pavement overlay will take place on either Wednesday or Thursday of
next week, as weather permits. The
paving operation will take place on Fisherville
Road from just south of Manor/Borough Road to the Sylvester Street
area. In an attempt to reduce traffic
delays, road box construction on North
State Street will be put on hold during the
paving. As stated above, we would
encourage commuters to avoid this area during the paving operation. Please stay tuned to the on-site message boards
for updates to the final paving schedule. We appreciate the public’s
patience during these often frustrating delays.

September 18, 2009 Update:
It is
anticipated that the final pavement overlay along the
Fisherville Road
corridor will take place the week of September 28th. In preparation for the finish pavement, crews
will be raising manhole frames and water valve boxes between Manor Road and Sewalls Falls Road. Visit www.concordnh.gov
or watch the on-site message boards for updates to the paving schedule.
Along the North State Street
corridor, the contractor continues installation of the new storm sewer
infrastructure between Roger
Avenue and Knight Street. We expect to begin removing the existing
pavement and sub-base from Sewalls
Falls Road south, and constructing the new road
box the week of September 21st. One-lane
traffic will continue during hours of operation and delays are to be
expected. Drivers are encouraged to
seek alternate routes whenever possible.

September 11, 2009 Update:
Next week,
the contractor will resume new drainage construction on North State Street,
between Roger Avenue and
Hutchins Street.
During this phase, single lane closures and delays are to be expected
throughout the remainder of pipe installation. The traffic signal
subcontractor has been on-site and has begun installation of the new
signal bases and hardware at both the Fisherville Road at Bog Road and North State Street at Sewalls Falls Road
intersections.
As major
construction efforts on the Fisherville
Road corridor are winding down, residents and
commuters can expect road crews to begin raising manhole and catch basin
castings to their finished elevations in preparation for the placement of the
final wearing course pavement. With the
continued cooperation of the weather, we are expecting to finish pave Fisherville Road,
from the northern limit of Phase I to the Aranco
Oil building in late September/early October.
Details will firm up as we move closer to the end of this month.

Fisherville
Road
September 4, 209 Update:
With
the completion of the Beaver Brook box culvert extension on the west side of Fisherville Road,
the contractor will focus efforts on building the new sidewalk in this same
area. New vertical granite curb,
guardrail installation, and base paving of the new walk will be the major
construction at the brook. One-lane
traffic conditions will continue throughout the week, with delays to be
expected during construction hours of operation. Work on the North State Street corridor will be
limited to replacement of existing domestic gate valves, from Tenney Street
to Knight Street. As always, we thank all citizens for their
continued patience with the traffic delays and we appreciate their concern for
the workers’ safety by slowing speeds as they pass through the work zones.

August 28, 2009 Update:
Next
week work will continue on the installation of the box culvert
extension and back slope construction at the Beaver Brook culvert crossing on Fisherville Road. During construction hours, one-lane traffic
conditions will persist and delays are to be expected. The new storm sewer construction on North State Street
will take a brief pause while National Grid and their subcontractor work
to retire the existing low pressure gas main.
Continental Paving will continue to replace domestic water gate
valves on North State Street
in the interim period.

August 20, 2009 Update:
New storm sewer infrastructure installation and domestic
water gate valve replacements will continue on North State Street from Sewalls Falls Road
to Tenney
Street. Residents and commuters should
expect one-lane traffic during hours of construction, with delays during peak
hours. On Fisherville Road, the contractor will
continue paving of sidewalks, restoration of disturbed areas and clean-up
efforts.

August 14, 2009 Update:
Next week,
installation of new storm sewer infrastructure will continue on North State Street
from Sewalls Falls Road south
to Roger Avenue. One-lane traffic conditions
will continue through the week and delays are to be expected. New sidewalk construction on Fisherville Road is
nearly complete with paving of the walks expected either this week or next.

August 7, 2009 Update:
Next
week, Continental Paving will complete fine grading of the newly constructed
sidewalks and pave them as well. The installation of new storm sewer
infrastructure on Fisherville Road,
around the Sewalls
Falls area, will continue
with one lane traffic conditions.

July 31, 2009 Update:
Next
week will bring continued storm sewer infrastructure improvements, mainly
focused in the Sewalls Falls Road
area of Fisherville Road, along with the replacement of
domestic water valves along North
State Street from Sewalls Falls Road to Hutchins Street. Construction of
new sidewalks along both sides of Fisherville
Road from Bog Road to Sewalls Falls Road is also scheduled for
the upcoming week, as the new granite curb installation is almost complete.

July 24, 2009 Update:
Next week
will see continued installation of new vertical granite street and driveway
curbing, new sidewalk construction, base paving of driveways and side street
aprons, and further installation of storm sewer infrastructure. This work will
be occurring on Fisherville Road
from Bog Road
to Sewalls Falls Road.
Replacement of domestic water valves to individual residences will also occur
in North State Street
from Sewalls Falls Road
to Roger Avenue,
as crews become available from completion of major construction efforts on
Fisherville Road. Drivers should anticipate one-lane traffic
conditions with delays expected during hours of operation.
July 17, 2009 Update:
After
some cooperation from the weather, Continental Paving has
placed binder coarse pavement on Fisherville
Road from Bog Road to just north of Sewalls Falls Road. The installation of vertical
granite curbing will continue into next week. Along with installation of curbing, the
contractor will focus on the construction of new sidewalks along both
sides of the street and base paving driveway aprons. One-lane traffic
conditions will continue and delays are to be
anticipated. We thank the public for its
continued patience during this work.

July 10, 2009 Update:
The placement
of select road base gravels, domestic water valve replacement and the majority
of new storm sewer infrastructure is complete. Next week, the contractor will
fine grade and base pave Fisherville
Road from Bog Road to just north of Sewalls Falls Road.
Significant traffic delays are to be expected during the paving operations.
Motorists are encouraged to seek an alternate route whenever possible.

July 2, 2009 Update:
Next
week work will continue on storm sewer and domestic water infrastructure improvements.
Upon completion of said, Continental Paving will be placing the crushed gravel
coarse of the new road box on Fisherville Road, from just north of Sewalls
Falls Road to Bog Road. These are the last few steps leading up to placing the
binder coarse pavements. With a little
cooperation from the skies, we hope to be paving the graveled section of road
by mid to late July. For all residents of the impacted neighborhoods and
commuters, thank you for your continued patience with the construction.

June 26, 2009 Update:
Next
week the contractor will continue to install storm sewer infrastructure in Fisherville Road and change out domestic water gate
valves. The new road box construction is
partially complete. Grading of the newly
placed recycled crushed gravel should also occur next week. Traffic will be one lane for the duration of
the week. Motorists are encouraged to
seek an alternate route if possible. The
public’s continued patience is appreciated.

June 19, 2009 Update:
Pending completion of the road box
construction, Continental Paving will focus on further storm sewer
infrastructure improvements in Fisherville
Road from Bog Road to Sylvester Street. This work will entail full road
crossings. One-lane traffic is to be
expected at all times during hours of construction. The City will also begin replacement of
existing domestic water valves to properties along the corridor. Impacts will be minimal. Affected property owners will be given
advance notice of service disruptions.
June 12, 2009 Update:
Next
week Continental Paving will begin removal of the underlying concrete slab in Fisherville Road
starting at Bog Road
working south to Sewalls Falls
Road. One-lane traffic is expected during
construction hours of operation, delays will be unavoidable. Please be advised
to seek an alternate route if possible. New storm sewer infrastructure
installation will also continue next week along with continued overhead wire
relocation to newly set utility poles. Continental has also mobilized and
activated a portable crusher in the Abbott
Road pit. We are currently crushing the concrete
slab that was removed from Fisherville
Road. during the first
phase of the project and recycling the material as select gravel road base for
the second phase of the work.
National
Grid and their subcontractor, R. H. White have completed service tie overs to the high pressure main in North State Street. The
next phase of the natural gas work will involve Sewalls Falls Road from N. State to 26 Sewalls Falls Road
also including First Street,
Roger Avenue
and Parmenter
Road.

June 5, 2009 Update:
Work continues along Fisherville
Road including the continued installation of new storm sewer infrastructure
south of Bog Road to the brook south of Rex Drive and from Sewalls Falls Road
north to Sylvester Street. Removal of
the street pavement and the underlying concrete slab will also begin; traffic
delays are to be anticipated. As always, your patience is appreciated.
May 29, 2009 Update:
The
next week will see continued installation of new drainage infrastructure in Fisherville Road
from Elijah Street
to Bog Road. One-lane traffic is necessary to facilitate
this construction and traffic delays are to be expected. National Grid
and R.H. White have completed the gas service conversions to the new high
pressure system in Fisherville
Road from Sylvester Street to Bog Road.
Additional gas service conversions in North State Street will continue for the
next month or so from Roger Avenue
to Sewalls Falls Road. Again, we thank you for your patience during
this heavy construction.
May 22, 2009 Update:
Next
week, Continental Paving will continue drainage installation on Fisherville Road
from Sylvester Street north
to Elijah Street. One lane traffic is
to be anticipated on a daily basis, alternate routes should be sought whenever
possible. National Grid and R.H. White continue to relay gas services in the
corridor, work will continue in North
State Street from Tenney Street
to Roger Avenue.

May 15, 2009 Update:
Next week,
work on the US Route 3 Corridor Improvement Project will continue,
with Continental Paving installing new drainage systems along Fisherville Road, from
Sylvester Street north. One-lane traffic is expected at times and delays
should be anticipated. The motoring
public is advised to seek alternate routes whenever possible. R.H. White and National Grid will continue to
relay gas services on both North
State Street and Fisherville Road.

May 8, 2009 Update:
On Monday, construction
will begin on Phase 2 of the US Route 3 corridor project with
the installation of drainage systems along Sylvester Street. The temporary closure of Sylvester Street, from
Sewalls Falls Road
to Fisherville Road,
is expected at times. This will include
no through traffic on Margerie Street. The
contractor will continue construction of the new gas mains along Fisherville Road,
as well as the replacement of services along North State Street, all in advance of the
major street work. Unitil and FairPoint Communications will begin to relocate utility
poles along Fisherville Road,
from Bog Road south
to the Beaver Meadow Brook. This work
will include underground conduit installation on Rex Drive.
May 1, 2009 Update:
Construction
continues along the US Route 3 corridor with the installation of drainage
expected next week on Sylvester
Street to Fisherville Road. Road closure is
expected on Sylvester Street,
from Sewalls Falls Road
to Fisherville Road,
to accommodate the pipe construction.
Delays are expected.

April 24, 2009 Update:
Phase I
improvements to the Route 3 corridor are nearly complete. The
pedestrian refuge islands are in place, as well as the concrete tip downs with
detectable warning panels. The sidewalk along the west side of Fisherville Road is
nearing completion with only small gaps remaining to be paved. The contractor will continue, as weather
permits, to place loam in the newly created grass panel and finalize the work
in this area.
Phase II
improvements to the Route 3 corridor are scheduled to begin in the next
week. This second phase of the reconstruction of Fisherville Road/North State Street will
begin at Bog Road
and progress south to Lake Street.
The contractor, Continental Paving, Inc., will focus on removal of granite
curb, asphalt road surface and the underlying concrete slab.
Traffic delays are anticipated and alternate routes should be sought if
possible. The public’s patience with this necessary work is greatly
appreciated.

April 17, 2009 Update:
Construction along Fisherville Road
continued this week, including installation of curb throughout the remaining
portions of the Phase I section of the project. The contractor has begun
addressing base paving of the sidewalks, curb trench patch, and driveway
aprons. Work will also focus on completing the new pedestrian refuge islands
along Fisherville Road.
Final restoration of disturbed areas with loam and grass seed should be
expected in the upcoming weeks. The gas company's subcontractor continues to
make good progress with the installation of a new main from Elijah Street northerly. The public’s
continued patience with traffic delays is appreciated.

April 10, 2009 Update:
Construction
of the Phase 1 improvements continue with curb and sidewalk construction along Fisherville Road.
Next week’s work will include constructing sidewalks from Scott Avenue to Bog Road, behind the newly installed
granite curbing; and continuing to address punch list items remaining from
winter shutdown. R.H. White has begun installation of a new gas main at Sylvester Street,
working north to complete the gas main section just south of Bog Road. As always, traffic delays are
to be expected. As a reminder to the traveling public, please slow down prior
to entering the construction zones - delays are frustrating but speeding
through a work zone is costly and dangerous.

April 3, 2009 Update:
Construction started this past
week along Fisherville Road
in conjunction with the US Route 3 corridor project. Work focused on
construction of sidewalks and shoulders along the west side of the roadway just
south of Cremin
Street. Next week construction will continue on new sidewalk along the
west side of Fisherville Road from Scott Avenue south to Bog Road. Curbing installation is expected to begin next
week along the newly constructed sections of sidewalk. Continental Paving
will also focus on punchlist items remaining from the
winter suspension of work. National Grid and their contractor R.H. White
will mobilize and begin construction next week of new gas main from Bog Road south to Sewalls Falls Road. Traffic delays are to be anticipated.

March 27, 2009 Update:
As
better weather approaches, so does the 2009 construction season. The Engineering Services Division is pleased
to announce the start of construction on the US Route 3 Corridor on
Monday, March 30th. Continental Paving
will continue its efforts on completing improvements on the first phase of the
project (Fisherville Road
from Bog Road
to Borough Road). Work is expected to begin on the second phase
of the project (Fisherville Road
and North State Street
from Bog Road
to Lake Street)
in mid to late April. Message boards
were deployed on Wednesday notifying the traveling public of the impending
work. Details on actual construction
sequencing and work area phasing will follow. Motorists should expect delays
during construction and are encouraged to seek alternative routes.