February
3, 2012 Update:
Work
continues on the culvert rehabilitation in the vicinity of the NH State
Prison/Palm Street along North State Street. Crews continue to evaluate the
existing stone masonry culvert and prepare the walls and floors for grout
sealing and Shotcrete surfacing. This trenchless
culvert restoration work is expected to continue through February. No traffic
delays are expected along North State Street.

January
27, 2012 Update:
Work
continues on the Culvert Rehabilitation Project on North State Street, just north
of the State Prison. Next week the contactor will concentrate on water
control and preliminary Shotcrete applications for
stabilization. No traffic delays are expected

December
9, 2011 Update:
All major construction items have been completed for the season on the North State Street corridor. Next week the contractor will be addressing street sign installations and clean-up. Minor delays should be expected from Hillcrest Avenue to the NH State Prison. We would like to thank the residents and businesses of the corridor, commuters, pedestrians, and cyclists for their patience and input on the project. Your continued feedback helps the City and the contractor make the end result of the construction the best it can be for all. We look forward to an early spring continuation of the rehabilitation effort of the Route 3 Corridor.

December
2, 2011 Update:
Work on the Route 3 corridor nears completion for the season. The contractor continues to focus on housekeeping and punch list items. Delays next week will be minor, but should be expected as clean-up work will be occurring from Dolan Street to the NH State Prison.

November
23, 2011 Update:
With the work completed over the course of the short holiday week, all that remains to be completed on North State Street are street sign installations, miscellaneous clean up items, loam placement and stabilization. These final tasks will occur next week, from Hillcrest Avenue to the NH State Prison. Minor traffic delays are to be expected.

November
18, 2011 Update:
The construction season is rapidly winding down and the Route 3
corridor project is coming closer to seasonal winter shutdown. Next week, work
will entail paving of the sidewalk, raising utility castings, placing loam, and
miscellaneous clean-up efforts. These activities will be taking place on North
State Street, from the City's Combined Operations and Maintenance Facility to
the NH State Prison. The contractor will be working only Monday through
Wednesday, due to the Thanksgiving Holiday.

November
10, 2011 Update:
Installation of the vertical granite street curbing was delayed this past week. Instead, the contractor addressed unfinished work north of the City's Combined Operations and Maintenance facility (COMF) and striped the newly placed pavement. Next week, the curbing will be installed and driveway aprons will be removed, graded to the new asphalt road surface, and base paved. This work will require one-lane traffic conditions. Delays are to be expected.

November
4, 2011 Update:
Despite the early snow storm, the contractor perseveres with the reconstruction of North State Street. With base pavement placed on the main line, efforts next week will consist of installation of the vertical granite street curbing. As with past weeks, work will be occurring on North State Street, from the City's Combined Operations and Maintenance Facility to the NH State Prison. One-lane traffic conditions will persist in this area, with traffic delays to be expected.

October
28, 2011 Update:
The excavation of the road box nears conclusion on North State Street We expect finalizing the excavation and placement of select gravels early next week. Once this work is accomplished, the contractor will begin fine grading and preparing the new road base for paving. Construction will continue on North State Street, from the City's Combined Operations and Maintenance Facility to the NH State Prison. Traffic conditions will continue to be alternating one lane in this area with major delays to be expected. As the fall weather can be volatile, base paving schedule will be announced via the on-site message boards. We expect paving operations will transpire during the latter part of next week. Please stay tuned to the message boards for real time updates.

October
21, 2011 Update:
The storm sewer infrastructure installation is now complete and the excavation of the road box is underway. The contractor has opted to begin in the south bound lane and move south towards the NH State Prison. Once this lane is complete, the construction will shift to the northbound lane. Work will be occurring from the City’s Combined Operations and Maintenance Facility to the State Prison. One-lane traffic diversions will be in place daily in this area and major traffic delays are to be expected during this phase of the construction.

October
14, 2011 Update:
Replacement of the existing storm sewer infrastructure in North State Street, between the City's Combined Operations and Maintenance Facility (COMF) and the New Hampshire State Prison, is proceeding on schedule and should conclude next week, weather permitting. One lane traffic conditions will persist in this area and delays to be anticipated.
Accompanying the conclusion of utility improvements, the contractor will shift focus to reconstruction of the road itself. As in the past, the asphalt pavement, foundational concrete slab and existing earthen materials will be removed and replaced with select road base gravels. Major traffic delays are unavoidable during this phase of construction and the public is encouraged to seek an alternate route if possible.

October
7, 2011 Update:
Removal and replacement of the existing storm sewer system continues next week in North State Street; from the N.H. State Prison facility to the City's Combined Operations and Maintenance Facility (COMF). Work is progressing slowly due to the presence of granite boulders and ledge, coupled with the myriad of existing underground utilities. Placement of select gravels for the sidewalk, from Dolan Street to the COMF, will be nearing completion next week. Paving of the walk and placement of loam should be occurring next week in this area, along with miscellaneous clean-up efforts. One-lane traffic conditions will be in effect next week and delays are to be expected in the aforementioned areas.

September
30, 2011 Update:
The vertical granite street curbing was successfully installed on North State Street last week and drainage pipe work began in the vicinity of the NH State Prison facility. Next week, the contractor will continue storm sewer pipe replacement along North State, from the NH State Prison to the City's Combined Operations and Maintenance Facility (COMF). Additionally, the masonry subcontractor will be on-site raising utility castings, this work will occur in North State Street; from Dolan Street to the COMF. One-lane traffic conditions will be in place at both locations and delays are to be expected. We thank the public for their patience during construction delays.

September
23, 2011 Update:
Due to the rain last week, the base paving was not placed as scheduled. The last lift of base pavement has now been completed. The weather has set our schedule back and may continue to do so next week. The contractor plans to attempt to install the vertical granite street curbing and raise utility castings on North State Street; from the City's Combined Operations and Maintenance Facility (COMF) to Dolan Street. Travel will be restricted to one lane during hours of operation, typically 7 a.m. to 6 p.m. Delays should be expected in this area. Replacement of existing storm sewer pipe will begin anew next week as well, rain or shine. This work will be taking place in North State Street; from the COMF to the N.H. State Prison facility. One-lane traffic will be in place at this location as well and major delays are to be expected. The public is encouraged to seek an alternate route whenever possible.

September
16, 2011 Update
After the completion of base pavement this week, the contractor will now focus efforts on installation of guardrail, vertical granite street curbing, and construction of sidewalk on North State Street. This work will be transpiring in the area of the Hood milk plant; Dolan Street to the City's Combined Operations and Maintenance Facility. Traffic delays continue in this area, as one-lane traffic conditions will persist during these operations.

September
9, 2011 Update:
Despite the inclement weather, the contractor perseveres with the excavation of the road box in North State Street. The rain has hampered efforts slightly, but we still intend to fine grade the recently placed crushed gravel and base pave next week. This work will occur on North State Street; from Dolan Street to the City's Combined Operations and Maintenance Facility, just north of the State Prison. Major traffic disruptions should be expected next week and we encourage all to seek an alternate route, where possible. Due to the volatility of the weather, paving schedule will be announced via the on-site message boards, but we tentatively expect either Wednesday or Thursday of next week.

September
2, 2011 Update:
Work on the subgrade and placement of select gravels on North State Street is progressing well. As of today, the south bound lane is complete from Dolan Street to the COMF. Next week, work will entail the same procedure in the north bound lane in this same area. One-lane traffic conditions will persist and major traffic disruptions should be anticipated during hours of operation, typically 7 a.m. to 6 p.m. In honor of the Labor Day Holiday, and to comply with City ordinances, the contractor will suspend operations on Monday 09/05/11. If weather continues to cooperate, the contractor anticipates that base paving will occur mid-September timeframe. Please stay tuned to this website and the on-site message boards for further details.

August
26, 2011 Update:
The contractor has completed the pipe work phase in the section of North State Street, from Dolan Street to the City's Combined Operations and Maintenance Facility (COMF). Next week, work will consist of removal of the remaining asphalt pavement, underlying concrete slab and subgrade. Once the existing materials are removed, placement of select gravels and grading will occur. This construction will be taking place in the aforementioned area. Major traffic delays are to be expected as one-lane conditions will persist. Commuters are urged to seek alternate routes whenever possible.

August
19, 2011 Update:
Work on the North State Street corridor drainage improvements continue next week, construction will still be taking place along the frontage of the H. P. Hood plant. Pipe installation should be completed next week, one-lane traffic conditions will persist in this area and major traffic delays are to be expected. The contractor expects to pave sidewalks at the Rattlesnake Brook as well as Hillcrest Avenue to Dolan Street.
We would like to take this opportunity to respectfully request that while in queue during delays that motorists do not block driveway access to residences, business or commercial sites along the corridor. Signs have been placed at critical driveways that cannot be blocked, i.e. the New Hampshire State Prison facility located at #312/314 North State Street. Thank you for your courtesy during often frustrating delays to commuting.

August
12, 2011 Update:
The contractor continues to focus upon installation of new drainage facilities, pipe work will continue in North State Street along the frontage of the H. P. Hood plant. Traffic delays should be expected in this area as one-lane traffic conditions will continue during this phase of construction. Work in the base paved section; Hillcrest Avenue to Dolan Street, is substantially complete, minor clean up tasks will be executed next week in this area with minimal traffic delays anticipated. At the Rattlesnake Brook site, vertical granite curb has been set and we expect that sidewalk construction will begin as soon as possible. Traffic will be restricted to one-lane at this site as well; minor delays should be expected between Lake Street and Knight Street.

August
5, 2011 Update:
The replacement of the existing storm sewer infrastructure continues in North State Street near the H. P. Hood facility. One-lane traffic conditions will persist in this area and major delays are to be expected. Construction in the base paved section, Hillcrest Avenue to Dolan Street, is finishing up rapidly. We expect to be placing concrete tip downs, sidewalk finish pavement and road striping shortly. With the completion of the Rattlesnake Brook culvert crossing, our road contractor will soon be mobilizing to that area to complete curb and sidewalk construction. This work will require one-lane traffic, with minor delays to be expected between Knight Street and Lake Street.

July
28, 2011 Update:
Work continues to progress on the replacement of the storm sewer
infrastructure in North State Street, located at the H. P. Hood plant.
Installation of new reinforced concrete pipe will continue at this location
next week. One lane traffic conditions will persist and commuters can expect
major delays. Granite curb has been installed and utility castings raised in the base paved section; from

July
22, 2011 Update:
Work on the replacement of the granite box culvert, just north of H.P.
Hood has commenced and the contractor will be installing new storm
sewer pipe in this area over the course of the next few weeks. One-lane
traffic conditions will persist in this area, and major delays to traffic are
to be expected. Work in the section of North State Street; from

July
15, 2011 Update:
Next week the contractor will be undertaking the replacement
of an existing stone box culvert in

July
8, 2011 Update:
With granite curbing installation nearing completion, the
contractor will begin reconstructing the sidewalk and driveway aprons along the
east side of

July
1, 2011 Update:
With the base pavement completed on

June
24, 2011 Update:
Due to inclement weather
conditions this past week, the planned base paving of

June
17, 2011 Update:
The contractor has completed road box excavation on

June
10, 2010 Update:
Roadway reconstruction continues
this week through next along the southbound section of
June
3, 2011 Update:
Excavation of the road box is underway on

May
27, 2011 Update:
The replacement of the existing storm sewer infrastructure in

May
20, 2011 Update:
Despite the inclement weather, the contactor continues installation
of the new 30" reinforced concrete storm sewer replacing the existing
granite box culvert. Road work will continue in

May
13, 2011 Update:
Drainage construction replacing an existing stone box culvert that
emptied onto property located at

May
6, 2011 Update:
Work on the new storm sewer
infrastructure continues to progress on North State Street, construction
will continue in the area from

April
29, 2010 Update:
Construction of the 42"
reinforced concrete culvert crossing and the mechanically stabilized earth
retaining wall at Swenson Granite is complete. Work will still be taking place
in

April
22, 2011 Update:
Work on the removal and replacement
of the existing storm sewer infrastructure continues next week. The contractor
continues to focus efforts on the drainage system in

April 15, 2011 Update:
The contractor continues focus upon removal and replacement of the
existing storm sewer infrastructure in

April
8, 2011 Update:
During the upcoming week, the contractor will continue installation
of the new storm sewer infrastructure in

April
1, 2011 Update:
Work on the replacement of the existing storm sewer in

March
25, 2010 Update:
Despite the inclement weather, the contractor has begun the
installation of the new storm sewer infrastructure in

March
18, 2011 Update:
With the recent arrival of spring weather, we welcome back our
contractor Continental Paving, Inc. for the continuation of the third phase of
the Route 3 Corridor Reconstruction project. The contractor plans to mobilize
equipment and resume removal and replacement of the existing storm sewer
infrastructure in
December
3, 2010 Update:
With the arrival of colder temperatures, the Route 3 reconstruction
project is set to wind down for the impending winter months. The vertical granite
street curbing has been installed and base paved, and driveway aprons have been
temporarily paved for the winter. The contractor will focus efforts next week
on clean up items and street sign installations. Work will be taking place on

November
24, 2010 Update:
With the completion of the base course pavement, the contractor
will now begin the installation of vertical granite street curbing. This work
will be taking place on

November
19, 2010 Update:
The road box excavation is complete for the season on the
Next
week, installation of vertical granite curbing will be occurring in the base
paved section of
The
placement of the final wearing course pavement on

November
12, 2010 Update:
The road box excavation is almost complete for the season on the
The
placement of the final wearing course pavement on

November
5, 2010 Update:
Road box excavation continues next week on
The
seasonably cooler temperatures have impeded our schedule for placement of
the final wearing course pavement on the Phase II base paved section of

October
29, 2010 Update:
The construction of the new storm sewer infrastructure is complete
on the
The
road box excavation will commence in
Our
contractor is preparing last seasons base paved section, from south of

October
22, 2010 Update:
The contractor has brought a second pipe crew to the site in order
to expedite new storm sewer infrastructure construction. The pipe work next
week will be taking place in
National
Grid and their contractor, R H White, are scheduled to complete gas main
connections for both

October
15, 2010 Update:
Next week the contractor will be completing the new storm sewer
infrastructure construction at the intersection of

October
8, 2010 Update:
Next week the contractor will be completing the installation of the
new storm sewer system in

October
1, 2010 Update:
Work continues on the new storm sewer infrastructure upgrades in
the intersection of

September
24, 2010 Update:
Work continues to progress slowly on
the removal of the existing granite box culvert and installation of the new reinforced
concrete storm sewer trunk line in North State Street at Lake Street. The
work has progressed from the east to the west side of the street, with the
first of two road crossings completed. Next week the contractor expects to
begin the second road crossing at the intersection. Traffic will continue
to be restricted to one lane during hours of operation; typically from 7:00
a.m. to 6:00 p.m. The public is advised to seek alternate routes, if possible.

September
17, 2010 Update:
Next week the contractor will continue installation of the new
30" concrete storm drain trunk line in

September
10, 2010 Update:
Work on CIP 35, the

August
27, 2010 Update:
After a brief hiatus for the bidding process to occur, Engineering
Services Division is pleased to announce that the CIP 35, US Route 3 North
State Street reconstruction project is to resume. Staff hosted a preconstruction
conference on Monday outlining the details of the third phase of the
project (
|
|