Engineering Services Division - City of Concord, NH

CIP#51 - White Park

 

May 15, 2009 Update:

 

The contractor is continuing to hydroseed and work on the remaining landscaping items.  Installation of the wood guardrail along the parking lot will also continue.

 

 

May 8, 2009 Update:

 

The contractor will be finishing up the seeding and installation of the landscape plantings next week.

 

 

May 1, 2009 Update:

 

The new scoreboard for the Red Eastman Baseball Field has been placed.  Funding for the scoreboard was donated by the Concord High School Class of 1957. This past week's activities included installation of wood guardrail fencing along the parking lot and the placement of tree plantings.  In addition, the remaining sod for the competition field was installed and grading and raking of loam areas continued in anticipation of the remaining areas to be seeded early next week.  We continue to ask patrons of the park to stay off the competition field and all areas prepared for seeding.

 

 

April 17, 2009 Update:

 

Spring is here, better weather is back and Gordon Construction is scheduled to resume work at White Park next week. Work includes completing the sod placement on the baseball field, loaming and seeding in the open park areas and several punch list and maintenance items noted from last year's construction. The construction activities will limit public access to some areas of the park; therefore, the public is encouraged to read the construction signs upon arrival. All work is expected to be completed by mid-May.

December 12, 2008 Update:

 

Staff is pleased to announce that the City has received the 2008 Excellence in Concrete Award for the pervious concrete pavement at White Park.  Presented by the Northern New England Concrete Promotion Association at its annual meeting on December 9th, the Association recognized the excellence of project design, concrete specification and the construction of the pervious concrete parking area at White Park, noting its innovation to drainage solution, its appealing look within the context of the neighborhood and attention to detail during the placement.  In addition, the Association recognized the entire project team for its efforts including McFarland-Johnson, the design engineer; Gordon Construction, the site general contractor; and Frank Bernard Concrete, the concrete subcontractor.

 

November 21, 2008 Update:

Work on the Red Eastman Ballfield is nearly complete with dugouts, backstop wall and fencing work done this past week. The parking lot and landscaped islands are complete and expect to be ready for use in early January. Lighting fixtures were also completed this week. Work scheduled for next week includes final site grading, loaming and cleanup. The contractor will be expected to return in the spring for loam raking and seeding and any final cleanup needed prior to usage of the field.

 

November 14, 2008 Update:

 

Work continues at White Park, including construction of the dugouts and backstop walls, and placement of trees and landscaping materials.  Paving is scheduled for early next week - weather permitting - and will include the bituminous sidewalks and driveway aprons. The contractor expects to focus on final detail items next week, including the installation of lighting fixtures, final cleanup around the dugouts and placement of sod, as well as installation of guardrails and posts in the parking area.  Work is expected to wrap up for the season just before Thanksgiving.

 

                                      

 

November 7, 2008 Update:

 

Work continues at White Park, including the construction of the baseball field dugouts and backstop walls, the placement of sod on the Red Eastman Field and the installation of trees and landscaping materials throughout the park.  Clean-up of the work areas is expected to begin as early as next week, with work being completed just prior to Thanksgiving.

 

  

                                                           Construction of White Park dugout            Placement of sod on Red Eastman Field

 

October 31, 2008 Update:

 

Crews continue the placement of sod throughout the ball field and construction of the third base line dugout.  The infield nears completion with placement of the skinned material and irrigation.  The parking area has been completed along with the installation of granite curbing.  Final site detailing, including landscaping, sidewalks and walkways began this week and will continue through next.

 

 

October 24, 2008 Update:

 

Work continues at White Park, including the placement of sod and the construction of the dugouts on the Red Eastman Field.  Fill placement is all but completed and final grading, drainage and loaming is nearing completion.  Curbing was completed this week, with the final concrete pour expected next week.  By the end of next week, the park areas should be well defined and final landscaping will follow.

 

 

October 17, 2008 Update:

 

Sod was delivered this week for placement on the ball field.  Final paving in the rink area and rear access drive was completed.  Next week's work will focus on completion of the pervious concrete parking area and construction of the dugouts and backstop wall.  The contractor is shaping up the final grades in the open green areas and landscaping and lighting will follow in late October.  We appreciate the public's continued support of the project and remind everyone that the park areas under construction are closed.  

 

  

 

October 10, 2008 Update:

 

The transformation at White Park continues.  Crews have installed guard rail along the new access road off of Liberty Street; the concrete work has begun on the dugouts for the baseball field; irrigation systems are nearing completion and work on the pervious concrete parking lot continues.  The ice rink has been set in its final location, which will allow for year round recreational use.  Placement of sod on the Red Eastman field is just weeks away.

 

  

 

October 3, 2008 Update:

 

The construction work at White Park continues, including the placement of concrete for the pervious parking lot and the construction of the new access drive off of Liberty Street.  Work on the Red Eastman Field continues, including the placement of loam, installation of the irrigation system and construction of the spread footings for the dugouts and back wall.

 

                                       

 

September 26, 2008 Update:

 

Construction of the innovative pervious concrete for the new parking lot continues.  Crews have also been concentrating on screening and spreading top soil onto the competition ball fields.  The new access road off of Liberty Street nears completion, with paving scheduled for early next week. 

 

   

 

September 19, 2008 Update:

 

Work at White Park continues on pace, as work crews have begun to screen and place topsoil on the Red Eastman ball field.  Construction started on the new Liberty Street access drive, along with the construction of Concord's first pervious concrete parking lot.  Completion of the rear access drive and the ball field is expected over the next week, while construction of the parking area and skating rink continues.

 

  

 

September 12, 2008 Update:

 

Work at White Park continues with the focus being put on the pervious concrete pavement parking lot.  Work crews from Gordon Construction have spent the week preparing the drainage and sub grade in preparation for the concrete pour later in the month. Next week will expect to see preparation of the topsoil material for placement on the Red Eastman ball field and construction of the rear entrance drive to the park.

 

 

September 5, 2008 Update:

 

Work continues at White Park including the construction of the ball field and new parking area.  Placement of fill and stone for the pervious paving area, along with construction of the light pole bases, was completed this past week and is expected to continue next week.  The project remains on schedule and weather has been ideal for site construction.  Expect the placement of loam on the ball field late next week and preparation for the concrete parking area the week after.

 

   

 

 

August 29, 2008 Update:

 

The contractor, Gordon Construction, has concentrated efforts on the new pervious parking area at White Park.  Soil has been stripped to sub grade.  Work will continue at the parking area, bringing in clean fill material.  Construction will continue on Eastman Field with top soil scheduled to be placed next week. 

 

   

 

 

August 22, 2008 Update:

 

Work continues at White Park, including the installation of new curbing on Beacon Street along White Park.  This will improve drainage along the north side of the park that was a problem.  Work also continues on the improvements of the Red Eastman Field.  Approximately 12,000 cubic yards of fill material has been imported to the site to improve grading and drainage of the field.  Work expected next week will include the completion of the fill placement on the ball field, layout and preliminary grading of the parking area and the start of the rear access drive to the Recreation office.

 

                                   

   

 

                                                Red Eastman Field @ White Park                  Curbing installation on Beacon Street

 

August 15, 2008 Update:

Despite the rains this past week, work crews continue construction at White Park. Focus remains on bringing in the sand material to make up the base of the Red Eastman field. The Engineering Services Division anticipates sub-grade preparation to be complete early next week followed by the screening and placement of the topsoil. The new ball field grade will start to take shape by late August. Gordon Construction also expects to begin base preparation of the new parking area next week.

 

August 8, 2008 Update:

 

Gordon Construction continues the improvements to White Park. Although rain has hampered some of the work this past week, crews continue to import and place fill materials in the Red Eastman Ball Field area.  Placement of fill is expected to continue through the next week or so, along with the installation of curbing on Beacon Street

White Park construction

 

LIBERTY STREET SIDEWALK: In conjunction with the White Park and Liberty/Auburn/ Centre Street Roundabout projects, staff is negotiating with Continental Paving to complete the installation of the sidewalk along Liberty Street, from Centre Street to Franklin Street.  This project will fill a safety need for sidewalk along the back side of White Park.  Staff is working closely with the residents impacted by the sidewalk and have found a design solution to construct the sidewalk with limited impact to the front yards of those closest to the street.  Work is expected over the next few weeks.  This work will be coordinated with the White Park rear entrance drive work scheduled for the week of August 18th.

 

August 01, 2008 Update: Work continued on the White Park Improvement Project this week. Efforts have been focused on drainage work and the topsoil of the Red Eastman ball field.  Once completed, the contractor will begin bringing in clean fill and reconstruct the playing surfaces.

 

    

 

July 25, 2008 Update:

 

Construction is underway at White Park.  Gordon Construction began site demolition on July 14th and continues with water and storm drain utilities, along with stripping topsoil and placing fill throughout the park.  The Contractor is expected to begin construction of the new driveway entrance to the Recreation Office next week.  Curb and drainage improvements along Beacon Street are underway.

 

Construction underway at White Park

 

June 2008 Update:

 

Bid documents and plans have been advertised and released for bidding for the first phase of improvements to White Park including the reconstruction of the competition ball field, construction of a new parking area and access drives, relocation of the rink area and general site landscaping improvements.  Engineering and Purchasing coordinated a pre-bid meeting on May 30, 2008 where 20 contractors attended expressing their interest in the project.  Staff is quite excited with the outcome of interest in the project and look forward to a competitive bidding spirit.  Work is expected to begin at the site in late June/early July and continue through November.  The park will remain open during the work with work areas protected off to limit access.

 

February 2008 Update:

 

Final design is underway and nearing completion.  Staff expects to present the proposed site plan and new skate house building elevations and floor plans to the Planning Board and Architectural Design Review Committee in March.  Design completion is expected in late March for April advertising and bidding.  Work is expected to begin in early May and will include the construction of new parking facilities, the reconstruction of the baseball field and related access, utility, landscaping and lighting improvements.  This exciting community project is the result of the comprehensive park master plan study completed in the 2005.  Additionally, a HUD-EDI grant in the amount of $148,500 has been awarded for the construction of improvements.