Engineering Services Division - City of Concord, NH

CIP35 – US Route 3 Corridor North Project Update:

 

 

 

November 21, 2008 Update:

 

Paving on the southerly end of Phase 1 concluded this week, bringing the first phase of the project to substantial completion. Curbing and sidewalk construction is expected through this week and the first half of next week. Work is expected through early December - weather permitting - to complete as much sidewalk construction as possible before the winter break. One lane shifts in traffic are expected. No work is scheduled for Thanksgiving Day or Friday, November 28th.

 

 

November 14, 2008 Update:

 

Work continues along Fisherville Road with drainage construction in the vicinity of Dunkin Donuts and Duncraft this week.  Once this drainage work is complete, preparations will begin to pave the last portion of road work.  Paving is expected early next week from Bog Road to McDonald's - weather permitting.  Traffic will be shifted accordingly so the public should expect delays.  Once the road is paved, curbing and sidewalk work will begin in the southerly work area.  Sidewalk construction in the northerly limits of the project continues. 

 

                                              

 

This past week, survey began on the next phase of the work (Bog Road to Lake Street), with the intent of design beginning as early as next week.  By starting this early, we expect to get project documents ready for early spring to continue the work effort southerly by April 2009. 

 

November 7, 2008 Update:

 

Improvements to the corridor continue.  Next week, drainage construction and conduit work will take place at the intersection of Fisherville and Bog Roads, along with sidewalk construction.  Paving of the remaining gravel areas is scheduled for the latter part of next week.  Additionally, this past week, crews paved the worst sections of North State Street and Village Street affected by last year’s severe winter weather.  Pavement overlays were completed on North State Street from Foster Street to Rumford Street, Call Street to Dolan Street, and Lake Street to Sewalls Falls Road; as well as Village Street from Abbott Road to Bonney Street.

 

  

                                                            Shim paving on Village Street                  Concrete tip-down north of Douglas Street

 

October 31, 2008 Update:

 

Work continues along Fisherville Road, including the removal of the concrete slab to Bog Road and the placement of drainage structures.  Crews have been constructing the gravel base for sidewalks from the northerly limits of the project to Mayflower Drive.  Next week, conduit for future signals at Bog Road will be installed.  Traffic will be reduced to one lane around work areas.

 

  

                                                      Sidewalk removal in front of Duncraft               Road boxing by Lun Hing Restaurant

October 24, 2008 Update:

 

Curb installation along the northern areas of the project has been completed.  Slab removal and road boxing continues south to Bog Road and is nearing completion.  Traffic will be shifted to one lane during work hours.  Drainage between Irving/McDonald's and Bog Road will begin on Monday and continue through next week.  Sidewalk construction will also continue through next week.  Two lanes of traffic will be shifted around those work areas, with reduction down to one lane, at times, to get by drainage construction as necessary.

 

Curb installation near Mayflower Drive

 

October 17, 2008 Update:

 

Slab removal has begun, heading southbound from McDonald's/Irving to Bog Road, and will continue through next week.  Traffic will be reduced to one lane between 7:00 AM and 5:00 PM.  Curb installation began this week heading northbound from Irving to Thirty Pines Car Wash.  Two-lane traffic will be shifted, as necessary, to avoid work areas, with temporary reduction to one lane when sidewalk work occurs across from the curb installation.  National Grid continues their gas main work between Duncraft and Bog Road, and should be finished by October 22nd.

 

                                      

 

October 10, 2008 Update:

 

Pavement was placed this week along Fisherville Road.  Crews paved the corridor from just north of McDonald's to the work line at Thirty Pines.  Next week will bring the same intensive road reconstruction south of McDonald's and will continue to Bog Road.  With one way traffic at times, the public should expect delays.  Many thanks go out to all the residents and businesses that have endured the construction work.

 

Fisherville Road

 

October 3, 2008 Update:

 

Drainage installation continues between Penacook Place and Thirty Pines Car Wash, along with the relocation of fire hydrants.  One-way traffic will be in effect during work hours.  Removal of trees was completed along the southbound side of Fisherville Road, with minor traffic impacts.  National Grid's gas main installation will continue through next week.  Traffic will be down to one lane for a short pocket, which will move southbound as the work progresses.  Work will commence in front of Irving Gas Station and head south to Bog Road.

 

Relocation of fire hydrant in front of 1 Douglas Avenue

 

September 26, 2008 Update:

 

Roadway reconstruction work continues along Fisherville Road, between Cremin Street and Mayflower Drive.  Drainage work will continue next week, between just south of Pinehurst Drive (Penacook Place) and C.C. Tomatoes.  National Grid will continue with gas main installation between Bog Road and McDonald's, as they will be finishing pipe installation, working on the regulator pits, and beginning work necessary to charge the line and cross services over to the new main.  In all, the project is progressing well thanks to the full support of the public, as well as the residents and businesses along the work corridor.

 

 

September 19, 2008 Update:

 

Work continues on Fisherville Road as part of the US Route 3 Improvement Program.  The contractor continues to remove the concrete slab between the Irving Gas Station and Mayflower Drive through next week.  Traffic will be shifted to one lane through this section during construction hours.  Drainage installation will continue at various locations between Mayflower Drive and Thirty Pines Car Wash, with the largest concentration of work being around Thirty Pines.  Traffic will be shifted to two narrow lanes to get by the work, with temporary shifts to one lane as drainage crossings are built.  Again, the traveling public should expect delays and is encouraged to seek alternate routes.

 

   

 

September 12, 2008 Update:

 

Work continues on Fisherville Road, north of Mayflower Drive.  Roadway reconstruction on the northbound side has been completed and work has shifted to the southbound side this week.  Progress on the removal of the concrete slab has been exceptional.  Construction of drainage and the roadway reconstruction continues simultaneously.  Expect to see the roadway section north of Mayflower in gravel, prepared for paving later this month, before jumping to the next section south of Mayflower.  National Grid (gas company) expects to begin the replacement of their low pressure gas main along Fisherville Road, from the Irving Station back to a point south of the work limits (near Bog Road) next week.  The contractors are closely coordinating their work.

 

 

September 5, 2008 Update:

 

The contractor continues with the removal of the concrete slab and roadway reconstruction along Fisherville Road, just north of Mayflower Drive.  Construction of drainage within the work area, along with the continuation of the removal of the concrete slab, is expected through next week, along with close coordination with the utility companies.  Although traffic is being maintained, delays are expected at times.  The traveling public is encouraged to seek alternate routes.

 

 

 

August 29, 2008 Update:

 

Removal of the east (or northbound) half of the concrete slab running down the center of Fisherville Road, between Mayflower Drive and 650 feet north of Pinehurst Drive (Thirty Pines Car Wash), will begin today, and continue through next week.  Traffic will be reduced to one lane during construction hours.  After hours, traffic heading northbound will be on gravel, and traffic heading southbound will be on pavement.  There will be no work on Monday due to the Labor Day holiday. 

 

Excavation on Fisherville Rd., between Mayflower and Pinehurst Dr.

 

August 22, 2008 Update:

 

This week, Continental Paving began excavation work along the east side of the corridor, just north of Mayflower Drive, including demolition of the existing sidewalk and gravel panel to make way for the new roadway.  Utility companies have been at the site assessing limits of utility conflicts in an effort to plan for coordinated work.  Continental Paving plans to continue the roadway box construction from Mayflower Drive north, for the next week or so, in an effort to widen the corridor to accommodate the shifting of traffic.  Two-way traffic is being maintained - some intermittent delays are expected with the work.  Staff hosted a public construction meeting on August 19th at the Beaver Meadow School to address concerns of residents and let the public hear the schedule.  The well attended meeting was productive and demonstrates the City's commitment in working closely with the neighborhoods.

 

August 15, 2008 Update:

 

City Staff, Continental Paving (CPI) and the City's inspection engineering consultant met and walked the Fisherville Road project corridor from Bog Road to Borough Road this week in anticipation to start of work during the week of August 18th. During the walk-thru, staff met with a number of residents and businesses - all eager to see the improvements get underway. Six (6) new utility poles were set by Unitil. CPI expects to setup the project office, initiate the traffic control plan and layout the improvement areas during the early part of next week with heavier construction to start the by the end of the week.

 

August 8, 2008 Update:

 

Staff hosted a preconstruction conference on Tuesday outlining the details of the first phase of the Fisherville Road project (Bog Road to Borough Road).  Continental Paving is the selected contractor and reports a project start date of August 18th.  Preliminary work including layout, offset control, sign placement and site reconnaissance is expected next week.  A construction meeting has been scheduled for Tuesday, August 19th at 6:30 PM at the Beaver Meadow School.  Residents, businesses and the traveling public will be invited to attend to hear the Contractor outline the construction strategy and what to expect in the coming months.

 

August 1, 2008 Update:

 

A pre-construction meeting with the contractor and the utility companies is scheduled for Tuesday, August 5th.  Construction on the first phase of the corridor, between Bog Road and Borough Road, is anticipated to start the week of August 18th.  Work will continue through December.

 

July 25, 2008 Update:

 

Bids were opened on July 3rd and scope of work negotiations were completed this past week, enabling the City to enter into a contract with Continental Paving, Inc. to complete the first phase of the project - Bog Road to Borough Road.  Contract documentation is underway and staff expects to coordinate a pre-construction schedule with the Contractor and utilities during the first week of August.  Staff will also be coordinating a neighborhood construction meeting to review the contractor’s schedule and work limits.  Work is expected to begin in early August and continue through December.

 

June 2008 Update:

 

Bid documents and plans have been advertised and released for bidding for the first phase of the multi-phased corridor improvement project along US Route 3.  The first phase of the project - improvements along Fisherville Road from Bog Road to Borough Road include the removal of the concrete road slab, construction of drainage and sidewalks improvements along with the installation of traffic signals at Bog Road and Fisherville Road.  A pre-bid meeting has been scheduled for June 17th for bids due back by July 3rd.  Once contractor documents are verified, work is expected to begin early July 2008 and continue through December.

 

February 2008 Update: 

 

Final design for the first two phases of the project (North State Street from Penacook Street to Rumford Street and Fisherville Road from Bog Road to Borough Road) is nearing completion.  Discussions with utilities and property owners are underway.  The design of the 1st phase of the project is expected to be complete in early March and released for advertisement and bidding by late March.  Construction along the corridor is expected in late April/early May.  As the Council will recall, the decision to remove the concrete slab underlying the bituminous pavement was made in February.  The project design was modified to accommodate this scenario.